Replacement dam unlikely

Feasibility study likely to nix roller-compacted concrete dam

By BILL MARDIS Editor Emeritus

A roller-compacted concrete dam to effectively replace the earthen section of troubled Wolf Creek Dam apparently is becoming less likely as time draws nearer for a final report on a feasibility study of the massive rehabilitation project.

Dave Treadway, public affairs specialist for the U.S. Army Corps of Engineers’ Nashville District, told the Commonwealth Journal this week that “ ... all indications point to a diaphragm as the most feasible, most cost effective, most workable plan.” He said a final report on the current study probably will be made the last of June.

“The report will give us enough information so we will know if we can rule out (a roller-compacted dam),” Treadway said. “If such a new dam appears feasible, more work will have to be done,” he added.

A diaphragm -- a four-to-five-foot-thick concrete wall extending through the earthen section of the dam and some 100 feet into the bedrock below the dam -- is the original plan and the one for which preparations currently are being made.

A contract for a diaphragm is tentatively scheduled to be let in December. It would be the second concrete wall extended through the earthen section of the dam. However, the diaphragm built during the 1970s was not as long or as deep as the planned structure.

A roller-compacted dam would be constructed with layers of concrete, each compacted with heavy equipment. The structure would be immediately downstream from the existing earthen section and would tie in with the existing concrete part of the dam. The earthen dam would remain and U.S. 127 across the dam would be undisturbed, according to early reports.

Lt. Col. Steven J. Roemhildt, commander of the Corps’ Nashville District, recently told the Commonwealth Journal that a roller-compacted dam would require lowering the lake level much lower than now, a situation unacceptable in a region where the economy is tied closely with the lake. He said the proposed diaphragm “will provide a permanent fix until the end of the (21st) century.”

Treadway, after discussing the new-type dam with Mike Zoccola, chief of the Corps’ Civil Design Branch, said building a roller-compacted dam would require “shutting down Wolf Creek Dam as we know it today ... and refilling the lake.”

“Would that mean draining the lake?” a reporter questioned.

“Basically,” responded Treadway. He said a completed roller-compacted dam would mean the entire length of the mile-long dam would be concrete. There apparently are no problems in the existing concrete section.

Lake Cumberland has been operating at 680 feet above sea level, about 43 feet below normal, since January. The water was lowered to ease pressure on Wolf Creek Dam, classified as in “high risk” of failure by a panel of outside experts.

Treadway said the drought in the Cumberland River Basin “ ... is actually helping” to maintain the current lake level. Pointing out that the Corps is required by law to keep nine feet of water in the navigable channel of the Cumberland River, Treadway said part of this mission has been taken over by Dale Hollow Lake.

print this story  

Photos


A final report on the feasibility of a roller-compacted concrete dam to replace the leaky earthen section of Wolf Creek Dam is expected the last of June. Corps officials say a planned diaphragm likely will prove more feasible than a roller-compacted dam. The new-type dam would force Lake Cumberland to be lowered to unprecedented levels during construction. Dennis Bolton Photo/ (Click for larger image)


Free Coupons



autoconx
Premier Guide
Find a business

Walking Fingers
Maps, Menus, Store hours, Coupons, and more...
Premier Guide
Premium Jobs

RN’s; LPN’s; SRNA’s.
Professional
Opportunities
Rockcastle Health &
Rehabilitation Center
a Signature Healthcare Commun
...>MORE

Behavioral Health Professional/ Therapist
Behavioral Health Professional/
Therapist
Individual Needed to provide Individual Family and/or Group Counseli
...>MORE

Hunting and Fishing
Hunting and Fishing
New Kentucky Outdoors Magazine is in Need of Sales and Distribution Personel. If you ever wante
...>MORE

See all ads

Premium Homes

New! 14x52 Clayton singlewide 2 br 1 bath. Price
New! 14x52 Clayton singlewide 2 br 1 bath. Price includes; delivery and set-up, central air conditioning installed, unde...>MORE

Use Part of Your Income Tax Return to Start Your Own
Use Part of Your Income Tax Return to Start Your Own Business. Be A Spa Consultant and Do In-Home Spa Parties. Great Mon...>MORE

Brand New Clayton 16x80 3 Br, 2 Ba Vinyl siding
Brand New Clayton 16x80 3 Br, 2 Ba Vinyl siding, shingle roof, and Thermopane windows. This gorgeous home details a larg...>MORE

See all ads

Premium Extras

Wiggington Builders
Wiggington Builders Inc. Brand New Finished to suit. 1225 sq ft up to 9800 sq ft. Office or Retail Space. Behind Montice...>MORE

Epperson Air
Epperson Air
Conditioning, Heating, Plumbing Electric Wish to partner with similar operating business and Assets.
...>MORE

Commerical Space for Lease Tradewinds
Commercial Space for Lease Tradewinds Shopping Center Hwy 27 Approx. 3000 sq ft. Former Bluegrass Cellular Building. Ca...>MORE

See all ads


 

Community Newspaper Holdings, Inc.CNHI Classified Advertising NetworkCNHI News Service
Associated Press content © 2009. All rights reserved. AP content may not be published, broadcast, rewritten or redistributed.
Our site is powered by Zope and our Internet Yellow Pages site is powered by PremierGuide.
Some parts of our site may require you to download the Flash Player Plugin.
View our Privacy Policy
Advertiser index